Current work being done on the arena includes installation
of rebar for elevated concrete deck pours at Main Entrance. Installation of
raker beams in the lower bowl to support lower bowl concrete stadia. Mechanical,
electrical, plumbing and fire protection rough-in. Installation of the upper
bowl HVAC ductwork. Interior metal stud wall framing. Interior drywall
installation at mechanical and electrical rooms. Exterior metal stud wall
framing at low roof parapets. Installation of exterior façade metal panel and
glazing systems. Installation and connection of underground utilities at L and
J Streets. Under-slab plumbing and rebar installation for event level slab
pours. Installation of roofing at the Practice Facility and arena low roof.
Source
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Golden 1 Center 5th & L Street |
Golden 1 Center 6th & L Street |
Golden 1 Center at 7th & K Street |
Golden 1 Center at 5th Street |
Golden 1 Center 5th & L Street |
Golden 1 Center 5th & J Street |
Golden 1 Center 5th & J Street |
Golden 1 Center at J Street |
Golden 1 Center at J Street |
Golden 1 Center from Embassy Suites on Capitol Mall |
Sacramento skyline seen from Yolo Bypass Wildlife Area |