Thursday, October 01, 2020

1215 O Street Office Building Construction



Construction Milestones:
  • Elevator work is in progress
  • Modular Systems Furniture installation has begun on Level 3
  • Site work continues along Neighbor’s Alley and will move to Pedestrian Alley
  • Gas and fire water line tie-ins are in progress
  • Raised access flooring installation is substantially complete Levels 2 through 11
  • Metal stud framing, MEP rough-in and drywall is in progress Levels 8 through 11
  • Installation of Penthouse metal panels is substantially complete
  • Roofing on Penthouse and Main Roof are substantially complete
Design Milestones:
  • Retail space design is in the approval stage
  • Interior graphics package design is in the approval stage
  • Furniture layout reconfigured for post COVID return to work scenario
  • Interior and Exterior art installations are in design with selected artists

    The project is scheduled for completion early 2021.


No comments:

Post a Comment