Wednesday, February 26, 2020

1215 O Street Project Construction

1215 O Street, Sacramento CA 


Construction Milestones
 
-Structural concrete is complete
-Windows are being installed from 9th to 11th floors
-Penthouse structural steel is erected
-Drywall framing is in progress through the 8th floor
-Mechanical & electrical work is proceeding through the 8th floor
-Raised access floor is being installed on the 2nd to 4th floors
-Ceiling painting in progress on 5th floor. Learn more herehere & here