Monday, March 21, 2022

2031K Street Mixed Bldg. Proposal

The Planning Dept. received plans to demolish the existing building at 2031 K Street and construct a new development with 296 mixed unit with 8 floors and 91 feet tall. Demolition requires historic evaluation as well as a deviation for height.  The proposal includes 233 studio units, 50 1-bedroom, and 13 2-bedrooms. Total square footage would be 250,595 sf. and 162 parking stalls. Documents submitted to Planning Dept. can be found at AgencyCounter.

Wednesday, March 16, 2022

The California Tower & Aggie Square Plan

UC Davis Health Sacramento campus is undergoing a
 massive expansion over the next decade

The proposed California Tower will include a 16-story, 332-bed hospital facility and 5-story pavilion. The $3.75 billion project is scheduled to have patients moving in by 2030 and is currently in the design development phase and will replace the north-south wing originally built in 1929 and the addition from the 1950’s and will be demolished in the coming years. These were images out of Comstock’s Magazine promotional supplement for March 2022. UC Davis Health is also investing 1.1 billion in the nearby AggieSquare where both research facilities and housing will improve the neighborhood.

The propose California Tower is expected to be completed in 2030

The 5-story pavilion adjacent to the California Tower

Thursday, March 03, 2022

New Tool to View Planning Activity

AgencyCounter is the City of Sacramento’s new online tool to easily view planning applications and proposed development projects in the city. 

Use the AgencyCounter to: Explore the map feature to view the planning activity and history for a specific property or area of the city. Sign up for an auto notification via email when a planning application is submitted within your chosen area of interest. Download the project application, project exhibits and other supplemental materials. Contact the assigned planner for more information or to submit comments on a project. View the AgencyCounter Scorecard to see projects under consideration by Council District and recently approved projects.

Wednesday, January 26, 2022

Lot X 30-Story Proposal

201 N Street - Southern Land Company proposal

In October of last year, the Southern Land Co. purchased Lot X (201 N Street) for $16.75 million in Downtown Sacramento and has since proposed building a 30-story residential tower with 237 units. The 2.5 acre site sits directly across from Crocker Park and would also include offices, retail, restaurant and parking for 426 vehicles. The project consists of residential tower rising up 350 feet with an open-air pool 165 feet high and a five story office building constructed with mass timber.

201 N Street - Southern Land Company proposal
I believe this proposal is far too large for Sacramento to support. It’s being marketed as a luxury high-rise apartment homes, but history has shown us that the only successful residential buildings built downtown in the last 40 years have been six and seven stories with 70 to 90 units. High-rises like this have higher costs for materials, to build this tall the rental costs will be incredibility expensive and I don’t think the demand will be high enough so that the cost pencils out. Thus far, no construction cost estimate has been given and ABC10 reports that the developer hopes to break ground in 2023. As of today, the Sacramento Planning office has not received any plans from the new owner for the Lot X address (201 N Street). I've been told plans will be submitted soon.
201 N Street - Southern Land Company proposal

201 N Street - Southern Land Company proposal

201 N Street - Southern Land Company proposal

201 N Street - Southern Land Company proposal

201 N Street - Southern Land Company proposal

Tuesday, January 25, 2022

Sacramento Skyline Photos

Sacramento skyline taken from 7.5 miles away on
 Levee Road 30 east of Davis
On these brisk winter mornings, the clarity when looking across the Sacramento valley can be perfect. One hundred miles away, the Sierra Mountains look to be an Alpine wonderland behind the Sacramento skyline. Both these photos were taken from the west looking east, one on county road 102 near woodland and the other on Levee road 30 east of Davis.
Sacramento skyline taken from 15 miles away
on County Road 102 near Woodland

Monday, January 24, 2022

Sacramento County Courthouse Construction

Driving east on Hwy 50 toward two concrete elevator shafts
It appears the Sacramento County Courthouse has almost reached its final height. The steel skeleton for the structure itself is going up around the two concrete elevator shafts that look to be topped out. Completion is scheduled for September 2023.

Sacramento County Courthouse construction

Sacramento County Courthouse construction
seen from the train station

Sacramento County Courthouse construction seen from 7th Street

Sacramento County Courthouse
construction seen from I-5

Sacramento County Courthouse construction seen from the train station

Sacramento County Courthouse construction
seen from the train station

Sacramento County Courthouse construction
seen from the train station

Sacramento County Courthouse construction seen from I-5

Sacramento County Courthouse construction seen from I-5

Sacramento County Courthouse construction seen from I-5

Sacramento skyline from Hwy. 50

Friday, January 21, 2022

Colliers Sacramento Office Snapshot: Q4 2021

The Sacramento office market is continuing to retract as public sector agencies continue to downsize. The national office market posted its first quarter of positive net absorption since the start of the pandemic, while Sacramento has seen seven straight quarters of negative demand and rising vacancy rates. Also noted in the Colliers Sacramento office report, the State of California accounted for a majority of occupancy losses. Read the Sacramento office report here.

Sacramento office market vacancy rate rose to 16.7 percent in Q4 2021

Thursday, January 20, 2022

1984 vs. 2022 Sacramento Skyline

Back in 1984 the dominate buildings in the Sacramento skyline were three state offices buildings that were built in 1964 and 1969 and a bluish green private office tower built in 1984 that came to be known as the Emerald tower. Today the skyline has grown equally by both the private sector and government office towers. My favorite is still the Emerald Tower (229 ft tall) also known as West America Bank Building. It’s interesting with the curved glass facing Capitol Mall and the steps moving up to the top of the tower. The skyline has evolved quite a bit in 38 years.


Wednesday, January 19, 2022

ENVOY Anthem Cathedral Square Construction

ENVOY at 1030 J Street in Downtown Sacramento
A tower crane rises over the 11th & J Street ENVOY construction site as the seven story building fills a corner that has been an eyesore for decades. After several proposals have come and gone, this project looks to be built with quality materials and should bring a lot of people into the area to live. There will be 153 rentals apartments above the retail on the ground floor. This stretch of J Street is in awful shape, hopefully when this is completed others in the private sector and the city government will push out the undesirables who bring down the area.  https://www.hrgarchitects.com/cathedral-square-mixeduse-apartment
ENVOY at 1030 J Street in Downtown Sacramento


Tuesday, January 18, 2022

1717 S Street Mixed-Use Construction

1717 S Street Mixed-use housing and ground floor retail

1717 S Street is a residential mixed-use project consisting of 159 affordable housing units and 11,376 SF of ground floor commercial uses. This project broke ground in March of 2021 and is expected to be completed in February 2023. When completed there will be 159 units (16 Studios, 119 One bedrooms, 24 Two bedrooms) regulated at low or very low income levels. The original cost was $62 million, but rising construction costs in the three years before ground breaking caused the price to rise to $80 million.

Wednesday, November 17, 2021

“Demolition by Neglect” for Capitol Annex

It's becoming very clear that the plan to demolish and rebuild the State Capitol Annex on the east end is the most secretive public project the State has ever tried to slip by the people. The more I learn about this horrible process as it’s slides through the approval process, the more I want it stopped all together. In the latest issue of Sactown Magazine, Rob Turner does some digging and finds that this entire project is being done in seclusion, everything from the underground parking garage to $1 billion cost to build a modern Annex replacement. At this late date in the approval process, neither design for the Annex or the underground garage have been made public.

The whole plan is also ill-timed as the Governor said he wants to explore the possibility of 75% of state workers telecommuting after the pandemic ends. So now should be the time state offices rethink how offices function. Also, as mentioned in the article, the only reason the annexation is in such bad shape is because for 70 years the Legislature found it inconvenient to their calendar to do major upgrades to bring deficiencies up to code along with other improvements. There’s a name for this in the world of historic preservation: “demolition by neglect.” Owners who have neglected historic properties often argue that they need to tear them down because they’re not up to code even if they were the ones who didn’t make those upgrades throughout the life of the property.

I highly recommend reading “No Annexation WithoutRepresentation” in Sactown Magazine.  

https://www.dgs.ca.gov/RESD/Projects/Page-Content/Projects-List-Folder/State-Capitol-Annex-Project

https://annex.assembly.ca.gov/

Friday, October 29, 2021

The ‘California Tower’ at UC Davis Medical Center

There is a new rendering for the proposed 16-story Califrornia Tower at UC Davis Medical Center. Expansion plans are underway for a $3.75 billion, 16-storty hospital tower at 1 million square feet.  Rebuild, Expansion at UC Davis Health




Wednesday, October 20, 2021

Luxury High-Rise Proposed For Lot X

In a partnership between Southern Land Company and the Sacramento Kings, a 28-story mixed-use luxury high-rise has been proposed at Capitol Mall and 3rd Street in Sacramento. What makes this project unique is that it would be constructed with mass timber. To learn more about this largely untested method, click here.

The Southern Land Company purchased the 2.56-acre site yesterday with great fanfare from nearby Crocker Art Museum and Sacramento Mayor Darrell Steinberg. The proposal would have 28-floors, 225 luxury apartments and 80,000 sf office space. Construction could begin as soon as 2023 and completed in 2025. At this time, neither a cost estimated or rendering have been given for the proposal.

I think this proposal is ridiculous at a time when nearly 2 million square feet of office space has been put back on the market in the last 18 months. Also, with so many others similar high-rise proposals failing over the years, I wonder what makes the developer this time think 225 high-end renters will want to reside there? Sacramento has successfully built and filled many mid-rises up to six stories, but not high-rises where the costs to build are much greater. Kings press release.

Wednesday, October 13, 2021

Colliers Sacramento Office Snapshot: Q3 2021

According to the report below, the Sacramento office market has shed 1.9 MSF in the last 18 months. The vacancy rate has risen for six consecutive quarters. The negative impact to the office market has been less severe than markets like San Francisco where the rate has more than doubled over last year.

https://www.colliers.com/en/research...n@colliers.com

Wednesday, September 29, 2021

The Fruit Bldg. Is Now The Exchange Hotel

This historic 10-story building built in 1914 has been converted from an office building into a boutique hotel. The Exchange Sacramento hotel has 100-rooms, rooftop lounge, basement fitness center and meeting room, and a restaurant and bar on the ground floor. Room rates appear to start at $285 a night an up. 


The Exchange Hotel - 1006 Fourth St., Sac. CA














Read more here: 
www.bizjournals.com

Thursday, September 23, 2021

Sacramento County Courthouse Construction

The Sacramento County Courthouse construction project appears to be poring two concrete elevator shafts and are currently on the 9th or 10th floors. Construction began in November 2020 and is estimated to complete in January 2024.

Sacramento County Courthouse construction looking south on 6ht Street

Sacramento County Courthouse construction looking east from I-5

Sacramento County Courthouse construction looking east from I-5

Sacramento County Courthouse construction looking east from I-5

Sacramento County Courthouse construction looking east from I-5

Sacramento County Courthouse construction looking east from I-5

Sacramento County Courthouse construction looking east from I-5

Sacramento County Courthouse construction looking south from 6th Street

Sacramento County Courthouse construction looking south from 6th Street

Sacramento County Courthouse construction looking south from 6th Street

Sacramento County Courthouse construction looking west from Gth Street

Sacramento County Courthouse construction looking north from H Street

Tuesday, September 21, 2021

Seven-Story Residential Project @ 1116 18th Street

Project rendering for 1116 18th Street by SKK Developers

Alfa Romeo Automotive at 1116 18th Street in mid-town Sacramento has demolished in favor of a seven-story residential project. The proposal would have retail/restaurant on the ground floor with the second floor becoming the developers (SKK) new office and then 24 units above. There will be not parking at the building, but across the street at 1801 L Street, parking will be dedicated to this project. Construction could start in late 2021 and be completed in 18 to 20 months. Back when I rode a motor scooter to work I used to bring it in to Alfa Romeo for repairs and tune-ups, really neat guy running the shop and fun place to observe a classic car/motorcycle repair mechanic. It will be missed.

Current automotive shop Alfa Romeo at proposed location

Friday, August 27, 2021

CADA Site 21 - 1330 N Street

It was only three years ago CADA put forth a taller nine story proposal at this location with 92 condos and I thought this was something Sacramento could support. This new proposal for the same location will have 17 condos and 75 apartments with retail space on the ground floor. This revision is proposed by HRGA Architecture and designed by Kohn Pedersen Fox and still needs planning permits approved by the city. It appears the materials used for the exterior of the building are a lower quality than the original proposal. 

Thursday, July 29, 2021

The A.J. Residential Project in the Railyards

The A.J. residential project in the Railyards
The A.J. is the first residential project at the Railyards to begin construction. It broke ground in August 2020 and is set for completion by Winter 2022. Located at the corner of Railyards Boulevard and 6th Street, the first Railyards mixed-use residential project, The A.J., will consist of 345 residential rental units, 69 of which will be affordable units, and 5,000 square feet of ground floor retail.

The A.J. residential project in the Railyards rendering