CADA has really come through in the redevelopment of 16
th Street.
East End Gateway 2 & 3 has turned out better than I had hoped. It took
seven years from proposal to completion and the results are fantastic. Development
Costs $26 million.
|  | 
| East End Gateway 2 & 3 | 
|  | 
| East End Gateway 2 | 
|  | 
| East End Gateway 3 | 
|  | 
| East End Gateway 2 & 3 | 
16
Powerhouse is moving right along. Work is currently being done on 6
th
floor and the installation of windows. This high-end, six story complex with
apartments going for $1,700 to $3,500 per month will be Sacramento's first
privately funded 
midtown housing development at $16.4 million. 
|  | 
| 16 Powerhouse | 
|  | 
| 16 Powerhouse | 
|  | 
| 16 Powerhouse | 
The Warren is just
starting to move the dirt around. This $34 million project is a far cry from
what was proposed there in 2007 link.
Construction ends first quarter 2015.
|  | 
| The Warren | 
|  | 
| Sacramento
City Unified School District-owned property | 
Sacramento City Unified School District-owned property… several proposals
being considered.