Tuesday, July 11, 2017

Hotel Tower Nearing Completion (22 photos)

Sawyer Hotel and Golden 1 Center at 5th & L Street Sacramento














The 16-story Sawyer Hotel and condominium tower on the north side of the arena plaza is about 70% finished. The tower will have 250-room hotel and 45 upscale condominiums and could open by late summer or early fall of 2017. The hotel tower is expected to cost $500 million.
Sacramento skyline with the Sawyer Hotel left center.
Taken from West Sacramento

View south down 6th Street from Railyards

Sawyer Hotel as seen from J & 4th Streets

Sawyer Hotel - A closer look at the odd placement
where the hotel below meets the condos above

Sawyer Hotel at 5th & J Streets

Sawyer Hotel J Street entrance

Sawyer Hotel J Street entrance

Sawyer Hotel J Street entrance

Sawyer Hotel on J & 6th Streets looking west

Sawyer Hotel as seen from K Street next to Golden 1 Center

Sawyer Hotel as seen from K Street next to Golden 1 Center

Sawyer Hotel as seen from K Street next to Golden 1 Center

Construction continues on the western portion featuring retail & entertainment

Construction continues on the western portion featuring retail & entertainment

Construction continues on the western portion featuring retail & entertainment

Looking west from the 16th floor of the Holiday Inn.

A closer look at the lower floors of the Sawyer Hotel

A closer look at the upper floors of the Sawyer Hotel

Sawyer Hotel on K Street


Continued work on the retail & entertainment
western side of the Golden 1 Center

Panoramic view of Sacramento looking west from the 16th floor
from the Holiday Inn

Monday, July 10, 2017

700 Block of K Street

700K is a $55.4 million mixed-use project that will bring of 250,000 sq. ft. of retail space, 137 mixed-income apartments. Construction is scheduled to be complete in the Fall of 2017.
700K
700K

The Ice Blocks

Ice Blocks Sacramento













The Ice Blocks are a three block area on R Street between 16th and 18th streets. The estimated cost at more than $50 million with three phases of construction include 145 apartments, 55,000sf retail, and 106,000sf office. All three phases are expected to be completed in late 2017 or early 2018.
Ice Blocks Sacramento

Ice Blocks Sacramento

Ice Blocks Sacramento

Ice Blocks Sacramento


Friday, July 07, 2017

21st & Capitol Ave. Parking Structure

21st & Capitol Ave. Parking Structure














Phase one of the proposed Whole Foods project is coming together. Even though Whole Foods is no longer going to be the ground floor tenant for the L Street second phase of the project, the parking garage intended to replace the parking structure that was to be demolished for the Whole Foods project is nearing completion.

21st & Capitol Ave. Parking Structure















The second phase is planned for 2001/2015 L Street that would include 41,000sf market on the ground floor. Above the market would be 141 residential units and parking. No date of when Phase two might start without a ground floor grocery store tenant.

Thursday, July 06, 2017

19J Demolition of Site

Demolition of building at 19th & J Street making way for
Mohanna Developments 11 story mixed-use building















The self-financed 11 story mixed-use apartment project started demolition of the site last Friday. The project would have 173 residential units and 6,600 sf of ground floor retail.

I’m surprised the city’s planning commission approved demolition without a solid date for when construction would begin. The central city has a terrible track record of clearing a portion of a block anticipating construction only to see it sit there empty for years or even decades. Mo Mohanna track record for finishing what he started is dismal as well. Back in 1978 his company built some homes in Rocklin, other than that his own website does not offer more than proposals that never were built. 

Demolition of building at 19th & J Street making way for
Mohanna Developments 11 story mixed-use building

Demolition of building at 19th & J Street making way for
Mohanna Developments 11 story mixed-use building

Demolition of building at 19th & J Street making way for
Mohanna Developments 11 story mixed-use building

Demolition of building at 19th & J Street making way for
Mohanna Developments 11 story mixed-use building






































































The cost of the project has not been stated but Mohanna Development bought the site last year for $2.5 million. I estimate the construction costs for the building to be around $50 million. Hopefully Mohanna will be able to build the project as planned, the central city could use some more housing.