View from West Sacramento with arena cranes in the air. |
Current work being done on the arena is installation of the
second primary box truss at the arena high roof. Installation, bolting and
welding of the arena high roof structure. Installation of high roof metal
decking. Bolting and welding of steel frame exterior façade support “ladders.” Application
of spray-applied fireproofing to steel. Mechanical, electrical, plumbing and
fire protection overhead and wall rough-in. Interior concrete masonry (CMU)
wall installation. Installation of interior metal stud wall framing. Installation
of exterior façade metal panels and glazing at south side of Practice Facility.
Installation of exterior façade metal panels and glazing at north side of
arena. Installation of utility vaults for permanent power feed to arena. Source
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Golden 1 Center 5th & L Street |
Golden 1 Center 4th & L Street |
Golden 1 Center 5th & L Street |
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Golden 1 Center Construction seen from the 12th floor of 555 Capitol Mall |
Macy's having solar panels installed on it newly installed roof. |
Golden 1 Center 6th & L Street |
Golden 1 Center 7h & L Street with recently installed facade |
Golden 1 Center 7th & L Street with recently installed facade |
Golden 1 Center at 7th & K Street |
Golden 1 Center at 6th & J Street |
Golden 1 Center at 5th & J Street |
Golden 1 Center at 5th Street |
Golden 1 Center at 5th Street |
Golden 1 Center at 5th Street |
Golden 1 Center looking south from I-5 |
Golden 1 Center looking south from I-5 |
No comments:
Post a Comment